The AI deployment cycle runs 12 to 18 months. The transformer procurement cycle now runs 2.5 to 5 years. A campus announced in 2025 cannot be operational in 2026 or 2027 unless its transformers were on order before the announcement. Wood Mackenzie projects a 30 percent supply deficit for power transformers this year, with demand in 2026 running 21 percent above 2024 levels.